August 2008 - Update

Frontage completed
Foyer Area
Main Gym area
Pits being Lined

The facility at this point is approx. 98% complete. Because of problems with the overhead traveling rig which runs above the tumble track and spanning 50mts, Continental Sports has been held up by about 4/5 days with their fitting.

The completion date of 28th August has now been missed but it is hoped that with additional fitters completion will be met by 5th September which will still allow the scheduled term start date of 8th September.

Fast Track area ready for lining

Bleacher seating
Sunken Trampolines fitted ready for lining